Updated Part 5: Amplifier, Cables and Conclusion (markdown)

ploopyco 2023-08-16 13:48:29 -04:00
parent 0c34e10529
commit 0692029d25
1 changed files with 4 additions and 0 deletions

@ -12,6 +12,10 @@ You will need the following:
- Amplifier Case Bottom
- 2 Small Screws
## OPTIONAL: Upload the latest firmware to the Amplifier
Now is a good time to do this, since the PCB isn't yet in its case. [Follow these instructions to upload the latest firmware](https://github.com/ploopyco/headphones/wiki/Appendix-C:-Firmware-programming#2-uploading-new-firmwares-to-the-amplifier); it should take about five minutes.
## Step 2: Place the Amplifier PCB into the Amplifier Case Bottom
![enter image description here](https://lh3.googleusercontent.com/pw/AMWts8B8t4TAn3mtP8Gdy1-sgzdmRx1KwWLLI9eUU2namoHEQzMG4Vu3P-1dIDiV0-FnfqG5r0tzLYcEPhnPZD2z2LiI6efDYq2DTI17r81kRbTYw8HSeMlvvRDpAFQ7GVeVT1KiCMrL9b8HYuLsyUUlAYXq=w1434-h955-no?authuser=0)